Moving structural steel into a constrained site
- Context
- A single 12-metre steel beam could not reach a site accessible only through a narrow inner-city lane.
- Contradiction
- The beam must be long to carry the load, yet length is exactly what makes it impossible to deliver.
- How the principle was applied
- Split the beam into shorter flanged sections bolted together on site.
- Outcome
- Delivered by small truck and erected without a large crane, at the cost of rigorous inspection of every bolted joint.